HS2 may cost £10bn more than planned
The proposed budget for the HS2 railway has increased by nearly £10bn to more than £40bn, the transport minister says.Andy Murray v Yen-Hsun Lu
The proposed budget for the HS2 railway has risen by nearly £10bn to more than £40bn, the transport minister has said.
Patrick McLoughlin told the Commons the new projected cost of £42.6bn, up from £33bn, would include a large "contingency" fund.He said the final cost could be lower than the new estimate, but said revising the figure was "right".
Some Conservative MPs are expected to vote against the High Speed Rail (Preparation) Bill later.
The new high-speed railway line is intended to link London to Birmingham by 2026, with branches to Manchester and Leeds, via Sheffield, planned by 2032.
The first phase budget is now £21.4bn, with £21.2bn for phase two. These figures include a contingency fund of £14.4bn across the scheme.
Mr McLoughlin said contingency money was built into the London Olympics budget but the cost ended up "below the price that had been set by the government".
"While I expect the final costs to be lower than those I have just outlined... this is the right way to plan the project," he told MPs.
He also said the new budget took account of "design and environmental changes to improve the scheme", including alterations to the route such as a tunnel under the M6 near Birmingham.
Continue reading the main story
The government has now put a new "ceiling" price on the completed project that is almost £10bn more than the previous "ceiling" price we had all been using.
The Department for Transport tells me they don't actually plan to spend £42.6bn - it just includes a huge contingency fund in case of problems.
The thing is, as anyone who has ever built an extension on their house will tell you, if you tell someone they've got a certain amount of money to spend, they tend to spend it, or even more.
So has the DfT made a rod for its own back by floating a bigger figure?
The headlines will probably now start calling HS2 a £43bn project (if you round it up).
In a few years time, will we all just assume that's the new price?
Analysis
How much will HS2 actually cost? Well, your guess is as good as mine.The government has now put a new "ceiling" price on the completed project that is almost £10bn more than the previous "ceiling" price we had all been using.
The Department for Transport tells me they don't actually plan to spend £42.6bn - it just includes a huge contingency fund in case of problems.
The thing is, as anyone who has ever built an extension on their house will tell you, if you tell someone they've got a certain amount of money to spend, they tend to spend it, or even more.
So has the DfT made a rod for its own back by floating a bigger figure?
The headlines will probably now start calling HS2 a £43bn project (if you round it up).
In a few years time, will we all just assume that's the new price?
Mr McLoughlin said scrapping HS2
would be the "easiest thing in the world" for the government, but the
long-term cost of that would be "huge".
He said building HS2 would "create and support" at least 100,000 jobs and "underpin" a further 400,000.HS2 could add more than £4bn to the economy before opening and would provide "around £50bn worth of economic benefits once it is up and running", he added.
Mr McLoughlin said the coalition was considering various compensation schemes for residents affected by the planned rail line, including a possible "property bond".
The bill, which would give the transport secretary power to spend money developing the HS2 line, is being debated at its second reading in the House of Commons.
A group of mainly Conservatives have tabled a rebel amendment, urging MPs to reject the bill until budgets and the route are determined.
The rebellion is being led by former cabinet minister Cheryl Gillan, whose Amersham constituency will be affected by the plans.
She said the project was "30 years too late" and added: "Technology and the whole of the UK is moving in a different direction."
Mrs Gillan's motion has been backed by 27 other Conservative MPs, plus four Labour, one Green, one Plaid Cymru and one independent.
But Labour backs HS2, meaning the government is expected to easily win the vote.
Shadow transport secretary Maria Eagle said HS2 was "essential", but voiced concerns about delays to the project.
Robert Oxley from the Taxpayers' Alliance described the project as a "white elephant", which would not deliver the economic benefits ministers claim.